Center Steps Apartments Exterior Front View

What's Happening
at the center

The Latest

Street Closure November 28th

November 21, 2018

Notice of upcoming street closure! Due to the tower crane erection on November 28th, 3rd Ave N. will be closed between Mercer St. and Roy St. between the hours of… Read More

Tower Crane Coming Soon

November 15, 2018

The parking garage excavation is almost completed.  The sides have reached the bottom of excavation and the 4th side (Roy/3rd) still has about 10 ft. to go, and should be… Read More

East Wall Drilling Complete

November 8, 2018

All of the drilling for the Eastern wall anchors has been completed – The contractor has hit the bottom of grade where the P2 parking level will be! Picture above… Read More

Dirt Moving

November 1, 2018

The excavation subcontractor, Fruhling, continues to remove dirt from the site. This week, the shoring subcontractor, Kulchin, continues to install the wood wall (lagging) to keep the soil from the… Read More

46,000 Cubic Yards of Soil

October 25, 2018

Pictured is the NE corner of the site as of Wednesday morning, with a lot more dirt removed! Since our last post, over eight thousand cubic yards of soils has… Read More

12 More Feet to Go on NE Corner

October 18, 2018

The NE corner of the site where the parking lot used to be is ahead of schedule so far for excavation. There is only 12 more feet to go to… Read More

Lagging Installed

October 11, 2018

Soldier pile installation has been continuing around the site. Pictured at left is the wood installed along the west wall, called lagging {which is anchored to the steel piles}, to… Read More

Scenes of Excavation

October 4, 2018

Excavation of the site for the future parking garage is underway! The excavation of the site to make way for the 2-level parking garage continues.  There have been some interesting… Read More

Start of Drilling

September 25, 2018

Drilling for the future parking garage will begin this week. This will entail a large drilling rig onsite to create holes every 8 feet around the perimeter of the site.… Read More

Site Prep and Erosion Control

September 20, 2018

Site clearing, grading and sidewalk saw cutting continues this week. Erosion control measures are also being installed (this reduces storm water runoff from the site when it rains) and consists… Read More

Concessions on select units*   Apply today!

Call us today to hear more information on rates, and schedule a tour! 833-564-5080

Restrictions apply contact leasing office for details*

Contact Us